High-Performance Job-Shop Scheduling 
With A Time-Delay TD(A) Network 
Wei Zhang and Thomas G. Dietterich 
Department of Computer Science 
Oregon State University 
Corvallis, Oregon 97331-3202 
{zhangw, tgd}research. cs. orst. edu 
Abstract 
Job-shop scheduling is an important task for manufacturing indus- 
tries. We are interested in the particular task of scheduling payload 
processing for NASA's space shuttle program. This paper summa- 
rizes our previous work on formulating this task for solution by the 
reinforcement learning algorithm TD(A). A shortcoming of this 
previous work was its reliance on hand-engineered input features. 
This paper shows how to extend the time-delay neural network 
(TDNN) architecture to apply it to irregular-length schedules. Ex- 
perimental tests show that this TDNN-TD(A) network can match 
the performance of our previous hand-engineered system. The tests 
also show that both neural network approaches significantly out- 
perform the best previous (non-learning) solution to this problem 
in terms of the quality of the resulting schedules and the number 
of search steps required to construct them. 
I Introduction 
In Tesauro's 1992 landmark work on TD-gammon, he showed that the temporal dif- 
ference algorithm TD(A) [Sutton, 1988] can learn an excellent evaluation function 
for the game of backgammon. This is the most successful application of reinforce- 
ment learning to date. The goal of our research is to determine whether this success 
can be duplicated in an application of industrial importance: Job-shop scheduling. 
We are interested in a particular scheduling problem: space shuttle payload process- 
ing for NASA. The goal is to schedule a set of tasks to satisfy a set of temporal and 
resource constraints while also seeking to minimize the total duration (makespan) of 
the schedule. The best existing method for this task is an iterative repair scheduler 
that combines heuristics with simulated annealing [Zweben e! al., 1994]. In [Zhang 
High-performance Job-Shop Scheduling with a Time-delay TD()) Network 1025 
and Dietterich, 1995], we report initial results showing that a neural network-based 
TD(A) scheduler can out-perform this iterative repair algorithm. 
To obtain those results, we hand-engineered a set of input features. An advantage 
of neural network algorithms, however, is that they can often learn good "features" 
(i.e., hidden units) from more primitive, raw features. The work described in this 
paper shows how to apply the time-delay neural network architecture [Langet 
al., 1990, LeCun et al., 1989] to this task to learn from raw features and thereby 
eliminate hand-engineering. 
In the following sections, we first describe the scheduling task and show how this 
task can be formulated for TD(A). We then discuss the problem of schedule rep- 
resentation and our network architecture. Following this, we present experiments 
on a set of simulated problems and discuss the results. These results show that the 
time-delay network using low level features can not only match the performance of 
the hand-engineered features--it can actually perform slightly better. 
2 The NASA Domain and TD(A) for the Task 
The NASA space shuttle payload processing (SSPP) domain requires scheduling 
the tasks that must be performed to install and test the payloads that are placed 
in the cargo bay of the space shuttle. In job-shop scheduling terminology, each 
shuttle mission is a job, which has a fixed launch date. Each job consists of a 
partially-ordered set of tasks that must be performed. Most of these tasks are "pre- 
tasks" that must be performed prior to launch, but some are "post-tasks" that take 
place after the shuttle has landed. Each task has a duration and a list of resource 
requirements. The resources are grouped into resource pools. For each task and 
each type of resource, the required amount of the resource must be obtained from a 
single resource pool. A complete schedule must specify the start time of each task 
and the resource pool by which each resource requirement of each task is satisfied. A 
key goal of the scheduling system is to minimize the total duration of the schedule. 
This is much more challenging than simply finding a feasible schedule. 
Zweben et al. [1994] developed the following iterative repair method for solving 
this scheduling problem. First, a critical path schedule is constructed by working 
backward and forward from the launch and landing dates; resource constraints 
are ignored. This critical-path schedule serves as the starting state for a state- 
space search. In each state of this problem space, there are two possible operators 
that can be applied. The PEASSIGN-POOL operator changes the pool assignment 
for one of the resource requirements of a task. It is only applied when the pool 
reassignment would allow the resource requirement to be successfully satisfied. The 
MOVE operator moves a task to a different time and then reschedules all of the 
temporal dependents of the task using the critical path method (leaving the resource 
pool assignments of the dependents unchanged). The MOVE operator is only applied 
to move a task to the first earlier or the first later time at which the violated resource 
requirement can be satisfied. The iterative repair method uses a combination of 
three heuristics to choose a task to repair. It prefers to move the task that (a) 
requires an amount of resource nearly equal to the amount that is over allocated, 
(b) has few temporal dependents, and (c) needs to be moved only a short distance to 
satisfy the resource request. The overall control structure of the algorithm applies 
simulated annealing to minimize a designated cost function. The search continues 
until a schedule is found that has no constraint violations. 
To view the scheduling problem as a reinforcement learning problem, we must de- 
scribe the problem space and the reinforcement function. We employ the same 
1026 W. ZHANG, T. G. DIETTERICH 
problem space as Zweben et al. The starting state so is the critical path schedule 
as discussed above. We define the reinforcement function R(s) to give a reinforce- 
ment of-0.001 for each schedule s that still contains constraint violations. This 
assesses a small penalty for each scheduling action, and it is intended to encourage 
reinforcement learning to prefer actions that quickly find a good schedule. For any 
schedule s that is free of violations, the reinforcement is the negative of the resource 
dilation factor, -RDF(s, so). The RDF attempts to provide a scale-independent 
measure of the length of the schedule, and this final reinforcement is intended to 
encourage reinforcement learning to find short final schedules. 
The RDF is defined as follows. Let capacity(i) be the capacity of resource type 
/--that is, the combined capacity of all resource pools of resource type i. At each 
time t in the schedule, let u(i, t) be the current utilization of resources of type i. 
We define the resource utilization index RUI(i, t) for resource type i at time t to be 
RUI(i,t) - max 1, capacity(i)J' If the resource is not over-allocated, RUI(i,t) is 
1; otherwise it is the fraction of overallocation. The total resource utilization index 
(TFIUI) for a schedule of length l is the sum of the resource utilization index taken 
over all n resources and all/times: TRUI -- in__l -].lt= 1RUI(i,t). Given these 
definitions, the resource dilation factor is defined as RDF(s, so) - 
Now that we have specified how to view repair-based scheduling as a reinforcement 
learning problem, we turn our attention to the learning algorithm. Suppose at a 
given point in the learning process we have developed policy r, which says that in 
state s the action to select is a - r(s). We can define an associated function f, 
called the value function, such that f(s) tells the cumulative reward that we will 
receive if we follow policy r from state s onward. Formally, f,(s) = =0/i(sj+x), 
where N is the number of steps until a conflict-free schedule is found. 
As in most reinforcement learning work, we will attempt to learn the value function 
of the optimal policy r*, denoted f* = f,., rather than directly learning r*. Once 
we have learned this optimal value function, we can transform it into the optimal 
policy via a simple one-step lookahead search. To learn the value function, we apply 
TD(A) as a form of value iteration. TD(A) is applied online to the sequences of 
states and reinforcements that result from choosing actions according to the current 
estimated value function, f. At each state s during learning, we conduct a one-step 
lookahead search using the current estimated value function f to evaluate the states 
resulting from applying each possible operator. We then select the action that 
maximizes the predicted value of the resulting state s . After applying this action 
and receiving the reward, we update our estimate of f to reflect the difference 
between the value of f(s) and the more informed value R(s') q- f(s'). 
3 Schedule Representation and Network Design 
The main challenge for designing a schedule representation is that virtually all 
methods for learning evaluation functions can only be applied to fixed-length vectors 
of features. However, the length of schedules varies depending on the number of 
tasks and the complexity of their temporal and resource constraints. In our previous 
work, we hand-engineered a fixed set of features that summarized the structure 
of the schedule. We included such features as the RDF of the current schedule, 
the mean and standard deviation of the unused resource capacity of each resource 
pool (negative if the pool is over-allocated), the mean and standard deviation of 
the slack times (idle times between temporal dependents), and so on. However, 
High-performance Job-Shop Scheduling with a Time-delay TD0) Network 102 7 
task 1 task 2 
I I 
task 3i task 4 
B1 B2 B3 B4 B5 B6 
Figure 1' The definition of "blocks". 
hand-engineering increases the cost of creating a new application and reduces the 
autonomy of the learning system. Therefore, we wish to develop a method that can 
automatically learn good input features. 
The time-delay neural network [Langet al., 1990] has proved to be very effective in 
learning good position-independent features in visual- and speech-recognition tasks. 
In speech recognition, it is applied to convert an input sequence of speech flames 
into a "hidden sequence" of extracted features. A classifier then walks along this 
hidden sequence and classifies each position in the sequence. The mapping from 
a particular position in the input sequence to a particular position in the hidden 
sequence is performed by a "kernel" neural network, which is scanned along the 
input sequence. It examines a sliding window of adjacent positions in the sequence. 
The kernel network has a single set of weights that are applied at all positions in 
the sequence, although each position may have its own bias weight. 
To apply this architecture to scheduling, we must solve two problems. First, we 
must define what a "position" means in the schedule. Second, we must decide how 
to use the "hidden sequence" of computed features. 
To define "positions", we subdivide the schedule into a sequence of "blocks." Each 
block is a maximal time interval in which the current tasks and resource assignments 
do not change (see Figure 1). For each block, we can compute primitive features 
such as the number of resource units available in each pool, and whether each pool 
is over-allocated. We also say that a task is "inside" a block if that task starts at the 
beginning of the block. Given this definition, we can compute additional primitive 
features of the tasks inside the block: minimum and average slack time, number of 
dependents, and number of tasks inside the block. If there are multiple tasks inside 
a block, we compute the average values of these features. A total of 12 primitive 
features are computed for each block. 
We then define five kernels, each of which examines a single "current block" and 
computes a hidden "feature" from this block. These five kernels are scanned along 
the entire schedule, and they create a derived sequence containing five "hidden 
features" for each block. How should this derived sequence be processed to compute 
the estimated value function? 
One approach would be to scan a network along the hidden sequence and take the 
maximum value output by that network. However, because our goal is to estimate 
the RDF of the final schedule, it seems wiser to view the kernels as learning to 
recognize "bad conflicts" and "opportunities". By summing (or averaging) the 
"hidden features", the network can effectively count the number of opportunities 
and conflicts and estimate how much more the RDF will change before the conflicts 
are eliminated. Hence, we take the following approach. 
The sequence of "hidden features" is split into thirds. Within each third, five 
1028 W. ZHANG, T. G. DIETTERICH 
features are computed by finding the mean value of each of the five hidden features 
over the blocks in this third. This gives a total of 15 features. These features, along 
with two other "global" features--the RDF of the current schedule and the resource 
utilization of the starting schedule--are input to a network having 40 hidden units. 
The output of that network is taken as the estimated value for the current schedule. 
To recap, the network has three hidden layers named Hi, H2, and H3. Layer Hi 
has 5 kernels (each with 12 weights). There are 15 biases, one for each feature 
in each third of the schedule. So H1 has a total of 75 parameters. H2 has 17 
units; 15 of these are hidden units (3 sets of 5) averaged from H1 and 2 of these 
are the two global input features. H2 has no adjustable parameters. H3 has 40 
hidden units fitlly connected to H2, for a total of 720 parameters. The output 
layer has 8 units fully connected to H3 and encoding the predicted RDF using the 
technique of overlapping gaussian ranges [Pomerleau, 1991]. The output layer has 
328 (= 8. (40 + 1)) parameters. Therefore, this net has a total of 1123 parameters. 
All units in H1, H3, and the output layer use sigmoidal transfer functions. 
4 Experiments 
We constructed an artificial problem set based on specifications for the NASA SSPP 
problem. Space constraints do not permit a complete description of the problems 
or the training procedure (see [Zhang and Dietterich, 1995] for full details). 100 
scheduling problems were generated. These were subdivided into 50 problems for fi- 
nal testing, 20 problems for validation testing, and three training sets of 10 problems 
each. An ensemble of 6 networks was constructed by training a separate network 
for each of these three training sets and for A = 0.2 and A = 0.7. Training was 
monitored by testing on the validation set every 100 epochs. Training was halted 
when the validation test showed no further change. For each of the 6 networks, 
the final set of weights and the set of weights giving the best validation score were 
retained for a total of 12 networks. 
Figure 2 compares the test set performance of six different scheduling configura- 
tions. GITDN is the mean test set RDF of the best single TDNN TD(A) network 
(as determined by validation set performance). G12TDN is the mean RDF of all 
12 learned networks. Analogously, G1N is the best single network trained using our 
hand-engineering features and G12N is the mean RDF of 12 hand-engineered net- 
works. IR-V and IR-RDF are Zweben's iterative repair algorithms using the number 
of violations and the RDF (respectively) as the error function to be minimized via 
simulated annealing. From this we can see that G1TDN produces schedules with 
better average RDF than any of the other methods. In particular the F test shows 
that it is significantly better than all other algorithms except G12TDN. 
Figure 3 compares the mean number of repairs required by each algorithm to find 
a solution. For the IR algorithms only repairs accepted by simulated annealing 
were counted. This shows that the neural network methods have learned very good 
evaluation functions--they are able to find a good solution much more directly 
than the simulated annealing methods. According to the F tests, the networks 
with engineered features are slightly better than the TDNN networks, but all of the 
networks are significantly better than simulated annealing. 
A shortcoming of these figures, however, is that they only record the mean results 
of single runs. Better results are typically obtained from simulated annealing if the 
algorithm is run many times and the best solution retained. Figures 4 and 5 show 
the mean RDF of the best schedule as a function of the number of schedule repairs 
and CPU time expended. IR-V and IR-RDF were each run 50 times; G12N and 
High-performance Job-Shop Scheduling with a Time-delay TD00 Network 1029 
1.46 
1.44 
1.42 
1.4 
1.38 
1.36 
1.34 
1.32 
1.3 
1.28 
55 
GI2N }GIN 
} m2TD3 
50 
45 
40 
35 
30 
25 
GIN 
t GI2TDN 
t G1TDN 
} IR-V 
Figure 2: Mean RDF values. Vertical error 
bars show 95% confidence intervals. Hori- 
zontal bars group together algorithms that 
cannot be distinguished based on ANOVA 
F-tests at p < 0.05. 
Figure 3: Mean number of repa/rs. Verti- 
cal error bars show 95% confidence inter- 
vals. Horizontal bars group together algo- 
rithms that cannot be distinguished based 
on ANOVA F-tests at p < 0.05. 
G12TDN show the results of running each of the 12 networks once on each test 
problem. G1N and GiTDN show the results of running the best single net 10 times 
on each test problem. Because evaluation function ties are broken randomly, these 
10 repetitions usually generate different schedules. Each time a network finds an 
improved solution to a problem, a point is plotted on the graph. 
The graphs show that the learned networks clearly out-perform Zweben's IR al- 
gorithms. Figure 4 shows that the networks perform many fewer repairs to find 
schedules of the same quality as the IR algorithms. Note that the horizontal axis is 
plotted on a log scale--the networks maintain a constant factor advantage over IR. 
For a schedule of a year's duration, this improvement would translate into several 
days (and hundreds of thousands of dollars) saved. 
Ultimately, G12TDN does slightly better than G12N. After 12 iterations and 21,676 
repairs, G12TDN produced solutions with an average RDF of 1.196. By comparison, 
G12N performs 19,406 repairs and produces an average RDF of 1.202. 
Figure 5 illustrates a problem with the neural network approach: the networks 
spend more CPU time selecting each repair. This reduces the differences between 
the methods. G12N exhibits the best tradeoff between CPU time and schedule 
quality, although G12TDN attains the best final schedule quality. 
The major CPU cost of G12TDN is the cost of breaking the schedule into blocks 
and convolving the kernel networks with the blocks. There are many opportunities 
to make this more efficient by taking advantage of the fact that each repair changes 
only parts of the schedule, and therefore, only parts of the neural network calculation 
need to be updated. 
Conclusions 
This paper has shown how to apply temporal difference learning to job shop schedul- 
ing problems by formulating them as iterative repair problem spaces. The paper 
has also presented a modification of the TDNN architecture appropriate for schedul- 
1030 W. ZHANG, T, G. DIETTERICH 
G12'I'N 
1.45 G12N ----. 
IR-RDF -B-- 
IR.V 
1.4 
1.3 
1.25 
1.2 
1.15 I I I I 
101. 2048 4096 8192 16384 32788  131072 262144 
Figure 4: Comparison of Accepted Sched- 
ule Repairs 
1.5 
1.45 
1.4 
1.35 
1.3 
1 2.5 
1.2 
1.15 
16 
32 64 128 256 512 1 (4 2048 
cPu True 
Figure 5: Comparison in CPU time 
ing problems. The combined TDNN-TD(A) architecture can learn very powerful 
search heuristics that significantly out-perform all previous algorithms in terms of 
the quality of the resulting schedules. The TDNN architecture achieves this high 
performance with much less "feature-engineering" than our previous neural network 
approach. This demonstrates once again the superior ability of neural networks to 
learn useful higher-level features from raw input features. 
Both of our neural-net-based methods demonstrate that the impressive performance 
of Tesauro's TD-gammon system can carry over to an important industrial appli- 
cation. Temporal difference learning is able to learn a very effective evaluation 
function for job shop scheduling. Using this function, a scheduler can find better 
schedules and find them in fewer search steps than the best previous methods. 
Acknowledgments 
The authors thank Rich Sutton and Monte Zweben for several helpful discussions. 
The authors gratefully acknowledge the support of NASA grant NAG 2-630 from 
NASA Ames Research Center. Additional support was provided by NSF grants 
CDA-9216172 and IRI-9204129. 
References 
[Langet al., 1990] K. J. Lang, A. H. Waibel, and G. E. Hinton. A time-delay neural 
network architecture for isolated word recognition. Neural Networks, 3:33-43, 
1990. 
[LeCun et al., 1989] Y. LeCun, B. Boser, J. S. Deniker, and D. Henderson et al. 
Backpropagation applied to handwritten zip code recognition. Neural Computa- 
tion, 1:541-551, 1989. 
[Pomerleau, 1991] D. A. Pomerleau. Efficient training of artificial neural networks 
for autonomous navigation. Neural Computation, 3(1):88-97, 1991. 
[Sutton, 1988] R. S. Sutton. Learning to predict by the methods of temporal dif- 
ferences. Machine Learning, 3(1):9-44, August 1988. 
[Tesauro, 1992] G. J. Tesauro. Practical issues in temporal difference learning. 
Machine Learning, 8(3/4):257-277, 1992. 
[Zhang and Dietterich, 1995] W. Zhang and T. Dietterich. A reinforcement learning 
approach to job-shop scheduling. In IJCAI-95, pages 1114-1120, 1995. 
[Zweben et al., 1994] M. Zweben, B. Daun, and M. Deal. Scheduling and reschedul- 
ing with iterative repair. In M. Zweben and M. S. Fox, editors, Intelligent Schedul- 
ing, chapter 8, pages 241-255. Morgan Kaufmann, 1994. 